445 MW SIEMENS ELECTRIC (2009/10) make, Combined Cycle Power Plant,
having the Following Technical Specifications:
PLANT DETAILS:
445 MW combined cycle plant the plant is based on Siemens V94.2 gas turbines.
The plant was installed in 2006, natural gas was available only from March 2009. The following
are the commissioning dates of various equipment.
GT # 1A – 30 March 2009
GT #1B – 10 March 2009
Open Cycle declared on 04 June 2009
STG was commissioned on 22 June 2010
Combined Cycle declared on 30 June 2010
The plant running hours as following:
GT # 1A = 32,361 EOH
GT # 1B = 22,913 EOH
STG = 19,460 EOH
STEAM TURBINE:
The operating hours of the steam turbine is 17900 hours.
GAS TURBINES:
Dehumidifier is built in feature of V94.2.
TECHNICAL DETAILS:
Equipment Manufacturer